Overall planning
- General CERN Injectors planning available on EDMS CERN-0000174579
- Tentative CLEAR Planning in 2025:
- Start of hardware commissioning : 17/02/2025
- IST Tests (access system etc) : 17/02/2025
- DSO Tests : 25/02/2025
- Beam Commissioning : ~03/03/2025 - ~07/03/2025
- Beam for Users: 10/03/2025 - 19/12/2025
- For more information or general requests please contact us!
Detailed CLEAR beam calendar:
This calendar contains the newest information about beam time blocks, as well as information about accesses etc. on a best-effort basis. You can also import it into your favorite calendaring tool using the iCal address https://calendar.google.com/calendar/ical/clearbeamcalendar%40gmail.com/public/basic.ics
For access to modifying the calendar, please contact Kyrre Sjobak or Pierre Korysko